Slide presentation summarizing corrective action activities at the former DuPont Waynesboro plant (April 10, 2013). Covers RFI background, SWMU investigations identifying mercury at SWMU 1 and 4, sewer impacts and interim measures (Fall 2010 sewer cleanouts), current Railroad Avenue interim measures (sewer repairs and filtration sumps), proposed source removals/capping, and a remediation schedule through 2015.
File Type:
pdf
Categories:
Presentations
Publication Date :
2013-04-10
Type :
Presentation
Review Notes :
The PDF is a slide deck dated April 10, 2013 and clearly a presentation. It does not explicitly identify a South River Science Team (SRST) meeting within the visible slides, so it was categorized as a standalone Presentation rather than SRST Meeting Documents.