This slide deck summarizes on-site corrective measures implementation (CMI) at the former DuPont Waynesboro plant (April 24, 2020). It describes active remediation at SWMUs 1, 4, and 7 (excavations, engineered caps, soil removals), interim sewer measures, planned AOC-3 sewer cleaning with bypass filtration, and next steps including final reporting and permit closure.
File Type:
pdf
Categories:
Presentations
Publication Date :
2020-04-24
Type :
Presentation
Review Notes :
The PDF is a dated slide presentation (April 24, 2020) and clearly documents remediation actions. It displays the South River Science Team logo but does not explicitly state whether it was delivered at a specific SRST meeting; therefore it is cataloged as a standalone Presentation rather than SRST Meeting Documents.