AECOM summarized a leaf-off maintenance inspection of the Allied Ready Mix Bank Management Area (BMA) conducted Feb 5, 2019 (memo dated Mar 4, 2019). Remediated banks were generally stable and rock toes intact, but December high flows displaced mid-bank container stock, exposing geocell and causing localized scour. Planned repairs include backfilling, fabric repair, and replacement plantings before the spring growing season.