Fact sheet describes Phase 1 riverbank remediation and restoration to reduce mercury in South River fish. It summarizes two remediation approaches—contaminated soil removal and capping using a biochar-and-sand mixture placed within geocells—notes initial work completed Feb 2017 at Constitution Park (Waynesboro), upcoming downstream work, and outlines monitoring, outreach, and contacts.
File Type:
pdf
Categories:
Fact Sheets
Publication Date :
2017-04
Type :
Fact Sheet
Review Notes :
Document date set to 2017-04 based on the PDF header reading 'NO. 8 • APRIL 2017'; no exact day is provided in the PDF.