Presentation (Oct 2015) outlining remedial design and stakeholder engagement for the South River remedy. Covers three objectives—reduce mercury loading, improve habitat, minimize disruption—updated Bank Management Areas and Phase 1A focus (RRM 0–2). Shows preliminary designs and restoration concepts for Constitution Park and North Park B, remedial methods (excavation, stabilization, biochar), and a construction schedule.
File Type:
pdf
Categories:
Presentations
Publication Date :
2015-10
Type :
Presentation
Review Notes :