Presentation detailing remedial design for South River Phase 1A bank management areas. Describes objectives and design criteria, layouts and cross-sections for primary and secondary BMAs at Constitution Park and WWTP A, including excavation, post-removal restoration, vegetative stabilization, and rock-toe protection. Includes projected mercury loading reductions (~90%) and a schedule for 2016 permits, design, and construction.
File Type:
pdf
Categories:
Presentations
Publication Date :
2016-04
Type :
Presentation
Review Notes :