Slide presentation (May 2015) summarizing remedial design planning for mercury-contaminated banks of the South River (focus on RRM 0–2). Covers remedial objectives, supplemental April 2015 bank core sampling, refinement of Primary and Secondary Bank Management Areas, estimated mercury loading, conceptual bank stabilization and habitat protection designs, and a schedule through early 2016.
File Type:
pdf
Categories:
South River Remediation Documents
Publication Date :
2015-05
Type :
Presentation
Review Notes :
Document is a stakeholder-facing remedial design slide deck dated May 2015. Category chosen as 'South River Remediation Documents' because content focuses on remediation planning; it could alternatively be filed under 'Presentations' if strictly treated as a standalone slide deck.