AECOM inspected bank stabilization at Shiloh Baptist Church after remedial work (Aug 26 and Aug 28, 2020) and found about 140 linear feet of surface erosion from RRM 0.60–0.63 where soils sloughed to the riprap toe exposing the geocell. The geocell remained intact. Recommended removing excess soil, place 1–2" planting substrate over geocell, seed, install erosion control blanket, replant/hydroseed, and water to establish vegetation.