August 2014 work plan describing Phase 1 interim measures for mercury-contaminated bank erosion in the South River (RRMs 0–2). The plan identifies ~1.3 miles of Bank Management Areas using hydrodynamic and regression analyses, outlines pre-design sampling, permitting, and monitoring, and lists potential actions (vegetative/structural stabilization, capping, removal) with construction targeted for 2016–2017.
File Type:
pdf
Categories:
South River Remediation Documents
Publication Date :
2014-08
Type :
Work Plan
Review Notes :
Date taken from text referencing the 'August 2014 Interim Measures Design, Implementation, and Monitoring Work Plan.' Authors (Anchor QEA, URS, DuPont) and targeted construction dates are stated in the PDF; no formal publication metadata or exact day-of-month was shown.