Final Technical Execution Plan presenting the rationale, design, and implementation details for Phase 1 interim measures at the Allied Ready Mix (ARM) Bank Management Areas (RRMs 1.33–1.59) in AOC 4. The report includes pre-design investigations, bank soil analytical data, H&H modeling, construction drawings and specifications, water and waste management, schedules, and appendices with lab, geotech, tree, and utility surveys.
File Type:
pdf
Categories:
South River Remediation Documents
Publication Date :
2018-02
Type :
Work Plan
Review Notes :
Date taken from the document cover (February 2018) so a month precision (2018-02) is used. The PDF is a Technical Execution Plan submitted as part of remediation; I selected document_type 'Work Plan' though it could also be cataloged as a technical report.