Slide presentation (August 2015) from Anchor QEA presenting a preliminary design update for Phase 1A bank management areas on the South River. Covers phased implementation, pre-design data collection (core sampling, geotechnical, tree and utility surveys), primary vs. secondary BMA remedies, cross-sections for Constitution Park and WWTP sites, and a permitting/construction schedule.
File Type:
pdf
Categories:
Presentations
Publication Date :
2015-08
Type :
Presentation
Review Notes :
Date and presenter taken from the cover slide (August 2015, Clay Patmont / Anchor QEA). No specific day is provided in the PDF; content is a slide deck presentation.